Traffic & Road Closure Updates

E-Notifier

See our new E-Notifier feature and sign up today. In order to receive up-to-date information, be sure to check the box for Traffic & Road Closure Updates. The E-Notifier will e-mail you whenever new information is added to this page.

Storm Updates and Road Closures

There currently are no road closures.

To receive community updates, including storm and road closures, please text "rpdps" to 888-777 or sign up online at www.nixle.com

Follow us on Twitter

For daily traffic updates and alerts, please follow us at @RPTrafficUpdate.

Rohnert Park Road Improvements Update: July 6, 2018

Enhancements to Rohnert Park Expressway -  University District Development: Brookfield Homes

Brookfield Residential has completed the first phase of reconstruction on Rohnert Park Expressway Eastbound. Traffic will now be routed onto the #2 lane (the slow lane) as work is commenced on the #1 lane (the fast lane). All intersections will be blocked from North or Southbound turns except at Kerry Road, where U-turns will be permitted. Detour signs will be installed to help with guidance to specific streets. Please follow construction signage.

To expedite construction, the City has modified the work hours to be from 7:00 am to 7:00 pm Monday through Friday. There will always be at least one eastbound lane open during construction. The westbound lanes will not be affected.

Jasmine Circle Residents:
During this time Jasmine Circle will be closed at Rohnert Park Expressway. Jasmine Circle residents will enter and exit at Snyder Lane.

Oak View Apartment Residents:
Now in the second phase, so if heading eastbound from Snyder Lane, residents will be unable to make a left hand turn into the complex. Residents could either enter on Medical Center Drive or continue eastbound on RPX and make a U turn at the signal at Karrington or Kerry.

Sonoma State University / Green Music Center:
The second phase of the project will not affect access at the campus. In this phase, when the intersection at RPX and Redwood Circle is being reconstructed, access to and from the Campus at Redwood Circle will be closed. A detour will be in effect guiding vehicles around the Campus via Petaluma Hill Road, Laurel Drive and/or East Cotati Avenue.

Thank you for your patience. Please obey all traffic control measures, drive safely and cautiously through the construction zone.

 



Construction work on Keiser Road this Week

Phase I construction work underway on Keiser Road (Between Snyder Lane and Petaluma Hill Road)

Crews are mobilizing and beginning various construction activities all along Keiser Road. At this stage during construction, there will be no access from Petaluma Hill Road to Keiser Road. Please access Keiser Road from Snyder Lane, access will be made available to local residents and Community Garden members only.

Potholing for existing utilities and grinding of Keiser Road is already underway. Work hours will be 8 AM to 6 PM. Flaggers will be present, expect delays of up to five minutes.

In addition, placement of a storm drain on Kerry Road will begin July 22nd and pipelines for domestic water installation will begin July 25th.

Thank you for your patience. Please obey all traffic control measures, drive safely and cautiously through the construction zone.